Update

Grading works, topsoil and the concreting to the infill section between fence and footpaths have now been completed in respect of phase 1c, fencing works are due to be completed this week, with the handover of this phase scheduled to take place on Monday.

In respect of phase 3a, demolition works are now complete to 8, 10, 12, 14 Hilderthorpe Road as are demolition works to the front section of numbers 16 – 18. We have installed scaffolding to numbers 20-22a Hilderthorpe Road, in readiness for commencing works to take down the slate tiles and roofing. Soft stripping works are also currently underway to numbers 20-22a.

Clifford House, Malmo Road, Sutton Fields Industrial Estate, Kingston Upon Hull, HU7 0YF
01482 823999
hull@hobsonporter.com Start the conversation
1 Marine Studios, Burton Lane End, Burton Waters, Lincoln, LN1 2UA
01522 305571
lincoln@hobsonporter.com Start the conversation
Name:
Message:

Copyright Hobson & Porter. All Rights Reserved 2014.
Web Design Hull - Mercury
Hobson & Porter Hobson & Porter
×
Menu