Home » Projects » Bridlington Infrastructure Works » Project Managers Blog

Project Managers Blog - Bridlington Infrastructure Works

Update - 30th June 2016 9:04

Work has continued to progress well on site over the last month. We have now completed the rubble clearing works in respect of Phase 4a of the project. Imported subsoil has been laid and graded to the required levels in this area and topsoil has been laid up to the line of the proposed fence.

 

We have also commenced work in respect of Springfield House.  Furniture has been removed from the building and we have begun the soft stripping works,

Update - 28th May 2016 12:51

Photos have been added to the gallery – keep up to date with the progress on site!

Update - 19th May 2016 13:39

We are now progressing work on site in respect of phase 4a of the contract – The demolition of 64-90 Hilderthorpe Road.

Over the last few weeks various works have been taking place including; – removal of asbestos roof sheets and artex from numbers 64-70 as well as fire doors and cement board from 86-88 Hildertorpe Road. A temporary road closure was put in place on Monday 9th May to enable gas service disconnection works to take place.

Update - 26th April 2016 10:50

New photos have been uploaded to the gallery!

Stay up to date with the progress on site.

Update - 7th April 2016 12:01

Work is progressing well on site with the Phase 3A demolition works now complete to 8-22a Hilderthorpe Road. This area has been cleared of rubble and grading and topsoil works are now in progress.

Additional work to an adjoining property is due to commence next week. These works will require the installation of a temporary scaffold enclosure involving the erection of structural support scaffolds.

Soft stripping works in respect of Phase 4A, 72-90 Hilderthorpe Road have commenced to some of the properties this week and these will continue into the forthcoming weeks.

Update - 25th February 2016 12:46

Grading works, topsoil and the concreting to the infill section between fence and footpaths have now been completed in respect of phase 1c, fencing works are due to be completed this week, with the handover of this phase scheduled to take place on Monday.

In respect of phase 3a, demolition works are now complete to 8, 10, 12, 14 Hilderthorpe Road as are demolition works to the front section of numbers 16 – 18. We have installed scaffolding to numbers 20-22a Hilderthorpe Road,

First Blog Post - 17th February 2016 11:50

Work is currently running to programme on the Bridlington Site. We are currently carrying out top soil, reduced level and fencing works in respect of phases 1c and 1d in addition to soft stripping works in respect of phase 3c. We are due to commence building dismantling works over the forthcoming weeks.

Clifford House, Malmo Road, Sutton Fields Industrial Estate, Kingston Upon Hull, HU7 0YF
01482 823999
hull@hobsonporter.com Start the conversation

    Name:

    Message:

    Name & Registered Office: Hobson & Porter Limited Clifford House Malmo Road Sutton Fields Industrial Estate Hull HU7 0YF
    Company No: 01448193

    Privacy Notice & Cookie Policy | Modern Slavery Statement
    Copyright Hobson & Porter. All Rights Reserved 2014.
    VAT Number: 317 3442 74
    Web Design Hull - Mercury