Marjorie Waite Court Extra Care Extension

Project Updates Back to Project

19/12/2019

What’s upcoming in early 2020?

We have a lot of key milestones in the early parts of 2020 – none more so than the demolition of the sports hall. We’ll be stripping asbestos straight after Christmas with the demolition – which will take around three weeks to complete – due to take place later in January.

The main build will continue to progress at a rapid rate now the building is mostly watertight, allowing interior trades to commence works.

In early spring the piling works will commence on the site of the former sports hall and we will be writing to residents again in the weeks leading up to this to give notice of these works.

Read more >
16/12/2019

Construction update: December 2019

The winter nights and cold temperatures might be here, but that hasn’t stopped the hard work on site and I’m pleased to say that works are progressing really well.

In the last update we spoke about the main build which will house the 29 apartments really starting to take shape with the first floor internal walls going in and works starting on the second floor. Since then the building has since been fully roofed and watertight from the gable end through to the lift shaft.

Read more >
15/10/2019

Construction Update: October 2019

The main build which will house the 29 apartments is really starting to take shape now, with the first floor internal walls going in and works starting on the second floor. The new entrance to Marjorie Waite Court on Crombie Avenue is now open and the old entrance is now locked and secure so that we can continue demolition and building works on this part of the site. Continue reading

Read more >
28/09/2019

Community Engagement Update: September 2019

On Thursday 26th September we were pleased to host a Macmillan Coffee Morning for residents at Marjorie Waite Court. The event was held to raise money for Macmillan to support people living with cancer. Continue reading

Read more >
23/09/2019

Community Engagement Update: August 2019

We have given a new bench to the residents of Marjorie Waite Court (MWC). It is currently located in a temporary position while our work continues but it will eventually be repositioned to a permanent place to be enjoyed by all residents. Continue reading

Read more >
23/08/2019

Construction update: August 2019

The new plantroom where the new boiler is housed, is nearing completion with the roof, insulation and flooring screed all complete. The mechanical and electrical equipment which will be installed in the plantroom over the coming months has started arriving at site. Continue reading

Read more >
23/07/2019

Community Engagement Update: July 2019

On July 18th we hosted our first residents’ coffee morning for the existing residents of Marjorie Waite Court. Keeping these residents up-to-date with the works and what it means to them is essential part of our stakeholder strategy for this project. Continue reading

Read more >
23/07/2019

Construction Update: July 2019

The build works to the new plantroom are nearing completion with the roof, insulation and screen all been installed. We have just started to take deliveries of the extensive mechanical and electrical equipment which will be installed in the plantroom over the coming months. Continue reading

Read more >
Clifford House, Malmo Road, Sutton Fields Industrial Estate, Kingston Upon Hull, HU7 0YF
01482 823999
hull@hobsonporter.com Start the conversation

    Name:

    Message:

    Name & Registered Office: Hobson & Porter Limited Clifford House Malmo Road Sutton Fields Industrial Estate Hull HU7 0YF
    Company No: 01448193

    Privacy Notice & Cookie Policy | Modern Slavery Statement
    Copyright Hobson & Porter. All Rights Reserved 2014.
    VAT Number: 317 3442 74
    Web Design Hull - Mercury